12.8.2022 Bartlett Street Public Information Meeting
December 12, 202212.8.2022 Bartlett Street Public Information Meeting
Bartlett Street Project Preconstruction Public Meeting, March 27, 2024
Go to the video of the meeting or the presentation link in the right-hand column of this page.
PROJECT UPDATE NOTICE
On Monday May 6, Albanese D&S will start daily closures, 7 am to 5 pm, of Bartlett Street between Woodbury Ave. and Hodgdon Brook. There will be a detour in place and the road will be re-opened every night.
Access to properties within the construction zone will be provided.Project Description:
This project includes the reconstruction of underground public utilities (water, sewer, drainage) on Bartlett Street from Hodgdon Brook to Dennett Street, and Thornton Street from Woodbury Avenue to Bartlett Street. This will also include connections to existing utilities on side streets of Morning Street, Clinton Street, Pine Street, Meredith Way and Woodbury Ave. The project also consists of reconstructing the streetscape, including curbing, sidewalks, reconstructing the roadway and traffic calming measures.
Project Manager:
Marc Batchelder, Project Manager
603-766-1440
mrbatchelder@cityofportsmouth.com
Start: April 9, 2024
Estimated Completion: Substantial: November 2024 Final: June 2025
Estimated Cost: $4,600,000
Funding Source:
Design Engineer: Marc R. Batchelder, P.E. / In-House Staff
Construction Engineer: Altus Engineering, LLC
Contractor: Albanese D&S, Inc.
Following the December 9, 2022 meeting, the City is moving forward with further discussion on this design option.
12.8.2022 Bartlett Street Public Information Meeting